Timeline and Cost Estimates / New Temple Project

Here is a quick over-view of the project's phases. The wheels are turning and much has been achieved to date.


Completed to date

  • Temple committee established

  • Consultation with Vastu experts in India.

  • Site search completed.

  • 24 acre site selected and paid for in full.

  • Architectural firm engaged and plans in progress.

  • Permission granted by Escondido city council.

  • Conditional use permit has been received.

  • Temple and cultural hall final design approved.

  • Environmental surveys completed and approved.

Status Report / Time Line

  • Timeline / Phase One
  1. Construction drawings completed by 1st quarter of 2007
  2. City Approval / Building Permit received 3rd quarter of 2007
  3. Construction Period / 20 to 24 months
  4. Grand Opening – 2nd quarter of 2009
  • Elements of Phase One
  1. Main temple building
  2. Prasadam hall / Dining hall
  3. Large kitchen
  4. Gift shop
  5. Parking
  6. Dormitory / Guest house
  7. Wedding area / festival lawn
  • Funding
  1. Projected cost/ budget remaining…..$8.5 million
  2. Funds either in the bank or committed……$5.75 million
  3. Balance required …….$2.75 million